傻貓
2019-1-30 21:10:08
mc有預contingencies, 計limit of retention都會包埋contin去計, 如果VO仲要扣, 咁咪扣上扣?
黃昏武士
2019-1-30 23:55:53
溫下書先啦師兄
:^(
Ads
冬甩爸爸
2019-1-31 00:00:38
:^(
錯哂 concept, btw main con 係會咁扼sub con Ge ,但真正concept 係剩係理contract sum ,計到個max retention 就係咁多 ,唔會因爲你vo幾多而要調多幾多上去。
黃昏武士
2019-1-31 00:27:15
總之一句講哂通常個Contract Sum係指Awarded Contract Sum
:^(
btw如果$1m-contract真係有$1m VO,情況會複雜得多
:^(
冬甩爸爸
2019-1-31 00:28:37
咁一係arch俾人吊屎忽 一係qs俾人吊屎忽
:^(
樋口彩
2019-1-31 00:52:18
多謝各位師兄教路
:^(
由maintenance 轉返new build contract 真係好多野pickup 返
Khwchan888
2019-1-31 06:39:06
Maximum retention is a value. You apply the retention percentage to the value of work done (both contract works and variation) in interim payment until that value is reached.
Khwchan888
2019-1-31 06:48:55
If like you said, the retention maximum is changed to a percentage then you have to find out how to apply that percentage. For example if the retention percentage is 5% as stated then you need to know what value to apply that stated 5%. Your question is unclear. If like a lot normal situation the contract states “retention maximum 5% of Contract Sum to the nearest thousand” then the retention limit will be 5% of the Contract Sum rounded to the nearest thousand dollars. In your example, the limit is 1Mx5% equals 50k, if that is the case. Thus you need to be sure what the Contract says.
傻貓
2019-1-31 07:09:24
開頭見到有人答 limit of retention會隨著VO而adjust都嚇左一跳, 但係問過其他人又話原來佢果間 Main Con 對 Sub Con的limit of retention真係會因VO而adjust, 所以上面話會變其實又錯唔晒, 真係睇合約點寫